Implementation
of MGNREGA in Odisha- A  Disaster
(Bulletin-2)
Inadequate
Human Resource Management 
Dear friends
As per the guidelines, a society for MGNREGS ( Mahatma Gandhi
National Rural Employment Guarantee Scheme) was formed  ( February 2007)  with four thematic experts, four specialists,
four programme Manager, six programme associates, four programme assistants and
six social audit managers. Similarly, 
the Govt. also declared  that one
additional Programme Officer (APIO), Computer Assistant, Account Assistant, two
MGNREGS Assistants ( MgA) were to be appointed 
for smooth implementation of  the
scheme at Panchayat Samiti level.  One Gram
Rozgar Sewak (GRS) and Gram Panchayat Technical Assistant (GPTA)  were to be appointed  at GP level. 
CAG has audited ( 2012 to 2017)  details of  
steps  taken   by Govt. in respect of appointment of
personnel  which are required  to enforce 
implementation of NREGA  in
Odisha.  It  was observed  that MGNREGS society  was functioning  with deficient manpower  as 14 out of 
28 required  officials  were not appointed . There was no Assistant
Computer programmer in 40 PSs, no GRS in 688 GPs and only one MGNREGS Assistant
in 192 PSs against the requirement of two. As all the  above mentioned posts are contractual, the
officials getting better employment opportunity leave the job.  
Maintenance of MGNREGS accounts, grievance redressal, on-line
entry of muster roll, verification and issue of Job Cards were not carried
out  as per the prescribed procedure. The
reason is  dfailure of Government  to provide adequate manpower  at the state 
and unit level. Because of it, the overall performance of the scheme suffered
in the state without yielding any 
tangible results. 
Pradip Pradhan
M-9937843482
Date-17.4.18 
 