Huge corruption, irregularities and kickbacks by OPTCL officials in Odisha

Huge corruption, irregularities and kickbacks by OPTCL officials while selecting   final bidder   M/s High Tech Systems & Services, Kolkatta, an authorised channel partner of M/s Tower Solutions Inc., Canada,  a Manufacturing Company for supply of ERS
( Emergency Restoration System) Materials for 400 KV transmission Line Network
(Exposed during inspection of ERS 400 KV materials under Right to Information Act)

( Mr. Hemant Sharma,  IAS   is serving  as CMD   of  Odisha Power Transmission Corporation Limited for 7 years- what for  and what is the interest of  Chief Minister office  to allow an officer to continue in a single post  for  7 years). 

Reason is only loot of public money. Here is cited  an example


Dear friends

RTI Act has not only empowered  citizens  to access information held  by the Public authorities but to inspect files, documents, work  and office of any public authority  following due procedure under the law.  Following section 6 of RTI Act, I had submitted RTI Application dt. 27.6.17 to the PIO, office of Odisha Power Transmission Company Limited ( OPTCL) , Govt. of Odisha   “seeking opportunity  of Inspection of Tower Materials  supplied  by Tower Solutions, Canada which has been  stored under DGM, ESP Store along with two Technical Expert .  All the documents relating to purchase and supply of quantity of materials by the company and proof of receipt of the materials by the authority should be available during inspection. The Technical team of OPTCL should be available to respond the query”.

On 1.7.17., My RTI Application was transferred to General Manager, E.H.T., Stores Division, OPTCL to provide me opportunity of inspection of materials.  But  my application was kept pending for 4 months  without any response and I was not allowed for inspection. When I filed first appeal dt. 26.10.17, the PIO immediately sent me  a letter for  inspection of materials. However, On 15.11.17, I was allowed for inspection of ERS materials in presence of store keepers of stores of OPTCL located at Mancheswar, Bhubaneswar.

Background of the inspection
From the RTI query it  was found that, in August, 2015,  OPTCL  had released  advertisement inviting  International Competitive bidding in e-tendering mode only from reputed manufacturer, type testing, inspection, loading at factory, transportation to & unloading at site / stores  including  guaranteed  obligation  for supply of lightweight  aluminium, modular type emergency  restoration system (ERS) suitable for  400kv transmission line Network  of OPTCL with an estimated  cost of  Rs. 130 Million.  Following   due tender procedure, OPTCL finally awarded this work to M/s High Tech Systems & Services, Kolkatta, an authorised channel partner of M/s Tower Solutions Inc., Canada,  a Manufacturing Company (?).

 As per Tender Advertisement, the bidder should be  a manufacturer or their authorised  channel partner  of 400KV  ERS tower for which he submits the offer. From the document produced  by the final bidder, it  was found that the major items like  Foundation Base plate, Foundation Base  Artiulation,  Tower sections ( TSMast), Universal attachment , Gin Pole etc.  are manufactured  and type tested  at  Laser  AMP, Granby, QC, Canada, whereas  the supplier is  “ Tower Solutions  Inc. , 7030 Woodbine Ave, Suite  500 , Markhan , ON L3R6G2, Canada, which  has claimed as manufacturing company at international level. While browsing the website, it  was also found  that Tower Solution , Canada  is  a Company having ISO 9001 certificate  for sales, engineering  and supply  of emergency tower for the high voltage  transmission industry, training of  electrical utility  companies  in using  temporary tower  and consulting to  electricity utility  companies.    It has also specialisation in transmission Modular Restoration Towers used for emergency restoration of high voltage transmission lines. It is a supplying-partner of Manufacturing Company Laser AMP, Canada.

Now the question comes, when Canada solutions is not a manufacturing  company, why and how OPTCL, a company functioning under Energy Department, Govt. of Odisha  awarded  work  to  a  fake  company  violating principle of advertisement   inviting bidder for supply of ERS materials.  Manipulating all procedures at direction of Hemant Sharma, IAS , CMD, OPTCL and preparing forged  documents , the officials  awarded   Tower Solutions, Canada  a fake manufacturing  company to supply the materials.  It was proved  during my inspection of materials on 15.11.17

On 15.11.17, I  along with my two RTI Activist-friends Sri Sachikant Pradhan and Sri Bikash Mohanty visited EHT Store sub-Division, Mancheswar to inspect the materials supplied Canada Solutions.  This ERS (Emergency Restoration Systems) material for 400 KV line network is essential   during emergency situation to ensure supply of electricity.  After  reaching on the spot, I met  General Manager, Stores Division and store-keepers  to show the materials and asked them  to  explain technicalities of materials.  They expressed  their helplessness to explain me details, as they do not have idea about  this technology. On query about who are the technical persons  of OPTCL having knowledge about this technology, they replied that no such technical person is available in OPTCL. I got astonished why OPTCL purchased  this  ERS materials, when it does not have expertise to handle it.

Then, while inspecting materials,  I asked   them to show name of  Tower Solutions, Canada  written   as manufacturer on  any item  of materials supplied .  After thorough search, I could not trace out  a single item manufactured  by Tower Solutions.  All the materials are  manufactured  by  company of Malaysia, China and USTower Solutions, Canada , claims to be manufacturer  company  is basically a supplier  company  which  we have already exposed and submitted complaint to Chief Secretary on 24.7.17  seeking  vigilance inquiry into it. 

Now, it is proved that how OPTCL  by manipulating all official procedure and preparing fake document   have selected a fake  company  i..e, Tower solutions to supply the ERS materials.    It was learnt that  crore  of rupees  has been given bribe to top officials of OPTCL to get the order. It was also learnt  that  “ this materials are not technically sound  and effective  to address the problem.  The company  has not supplied  genuine  and technically  viable materials”.  Though I persuaded  to take photograph of materials, the officials did not allow me to take it.

It shows  how Odisha suffers due  to  corruption and irregularities  engineered  by officials  under Nabin Patnaik, Chief Minister of Odisha, We will expose more corruption in OPTCL very soon.

Pradip Pradhan
RTI Activist, Odisha
M-9937843482

Date-16.11.17 